Ancorite have to receive orders and successfully completed 3 separate contracts for PG Tankers, installing new ballast water treatment system pipework. The Tankers we have completed the pipework installations are Georgina PG (April 2018), Lucy PG (April 2019) and Tessa PG (March 2020). Ancorite also have an order to install pipework in the Evie PG during October 2020 and are in discussions regarding the Veronica PG expected to be required early 2021.
The installation projects have all taken place in Port of Spain Trinidad and take approximately 14 days per installation, during this installation process Ancorite remove existing ballast water pipework, the existing pipework either GRP or steel. We then install and joint the GRE pipework and assist PG Tanker personnel to install all the instrumentation and apparatus. Once installed a commissioning team take over.